Good Morning,
I have a project in which our inspector has requested we megger every subfeed. I purchased a klien ET600 meter that has a 4000MEGAOHM maximum. We are running our test phase to phase and all of our runs say 4000MOHMS as our reading? Am I doing this wrong? Mostly 1/0-3/0 XHHW copper. 100-200 ft runs.
I am lost. Any feedback on how to megger would be much appreciated.
Thank you!