If you have a project where two 480V circuit runs were found to have damaged insulation after 6 months (ground fault) due to a contractor's poor installation techniques, how confident would you be of the integrity of all other circuits on the project that pass one-time 60sec meggering? What would you recommend to an owner for pass/fail?