Megging branch circuits

Status
Not open for further replies.
Does anyone know of an NEC, NETA or any other requirement to meg branch circuits after they are installed? From my personal experience, I always megged cables after install to CMA. Our contractor wants to get paid more to perform what I consider a standard QC practice.
 
Status
Not open for further replies.
Top