pbbbfischer
Member
- Location
- United States
I have a situation where the Service Utility provides the meter can, 200amp breaker and 3 sets of lugs below the breaker in one enclosure. (3-phase A lugs, 3-phase B lugs and 3-netural lugs) All on the meter pole. I will need to feed 3 separate buildings from this point. All will be burried in PVC directly out of this "all in one" meter can. I will have grounding electrodes at each building.
The utility has a grounding electrode on the bottom of the pole and an 8" rod next to the pole attached to the service neutral at the top of the pole. Is there a need for me to install another grounding electrode at that can before I feed the 3 buildings? Do I need to pull an equipment ground to each separate building or just bond each service entrance panel?
Thanks, Pbbb
The utility has a grounding electrode on the bottom of the pole and an 8" rod next to the pole attached to the service neutral at the top of the pole. Is there a need for me to install another grounding electrode at that can before I feed the 3 buildings? Do I need to pull an equipment ground to each separate building or just bond each service entrance panel?
Thanks, Pbbb