designer82
Senior Member
- Location
- Boston
A 40 unit multi-family condo building is looking to increase elec. capacity.
I'm not totally clear on what exactly they're looking to do but it sounded like the service to each dwelling unit has become undersized.
They want to add larger loads within the units, they mentioned electric heat pumps etc.
They also mentioned they want to add EV chargers, so I'll assume they want to also upsize their house panel as well.
1) Assuming a whole new meter center, demo/replace with new feeds to each dwelling unit & house panel. That's a huge amount of work obviously.
That kind of work cannot be done live and would need power shutoff to all building. Please give me a sanity check here to make sure I'm not overlooking anything.
2) If it ends up being less intensive, for example assume the feed to each unit is adequate & main service is adequate but the meter/breaker to each unit at the meter center just needs to be upsized. Could this be done live?
I ask because apparently they had some contractors tell them it can be done live & some tell them it can't be done live.
They don't want the tenants to lose power during the upgrades.
Thanks
I'm not totally clear on what exactly they're looking to do but it sounded like the service to each dwelling unit has become undersized.
They want to add larger loads within the units, they mentioned electric heat pumps etc.
They also mentioned they want to add EV chargers, so I'll assume they want to also upsize their house panel as well.
1) Assuming a whole new meter center, demo/replace with new feeds to each dwelling unit & house panel. That's a huge amount of work obviously.
That kind of work cannot be done live and would need power shutoff to all building. Please give me a sanity check here to make sure I'm not overlooking anything.
2) If it ends up being less intensive, for example assume the feed to each unit is adequate & main service is adequate but the meter/breaker to each unit at the meter center just needs to be upsized. Could this be done live?
I ask because apparently they had some contractors tell them it can be done live & some tell them it can't be done live.
They don't want the tenants to lose power during the upgrades.
Thanks