Do I need to bond the meter/disconnect panel? I looked on the diagram inside the panel and I didn't see where bonding should go.
Do I need to bond the meter/disconnect panel? I looked on the diagram inside the panel and I didn't see where bonding should go.
Depending on the type wouldn’t the #6 to the ground rod attachment be the bond?
If the meter/main is the service disconnect then your GEC(s) will terminate there on the neutral.
Perhaps some confusion about what the OP means by "bond". To me, that means the main bonding jumper connecting the case/EGC bus to the grounded conductor, as Texie mentioned. I guess it could mean the GEC connection to the grounded conductor also.