Been a while since I saw one of these:
(E) Meter only outside. No main breaker, no distribution.
I am planning for inspection. Electrician friend says it will fly.
I am not sure.
It feeds a 100A main breaker / 200A rated sub in garage.
We are installing
3 @ Enphase IQ5P batteries
6.72 kW PV system
Enphase Combiner 5
Skipping the Enphase Controller. (No battery backup, Grid tied battery and PV only.)
Do they need a new service?
Do I need to install a solar AC disconnect outside?
Would the Enphase Combiner suffice?