I work for a utility and management wants to put metering pts in pad mount transformers my concern is that the fault current that is avaliable in some padmounts 277/480 volt and working clearance. Im pushing to keep them in customers switchgear cold sequence for saftey reasns maybe im not on the right tract any thoughts ? Thanks