I am a site manager building the police training facility for the Iraqi's. My third country national electrical engineer told me I need 4 runs of 300mm2 (592.1 KCMIL) for each phase. The runs are about 30ft long from the generator to the manual transfer switch. I did some research in the code book and online and it seems for that distance one run of 300mm2 per phase and neutral would work. Could someone validate this for me?