Each apartment unit is fed by a 2-pole 50A circuit breaker. What is the minimum overcurrent protection required for each unit? Meter bank is indoors and provide power to each unit. Each dwelling unit panel is technically considered a sub panel.
225.39 only applies to branch circuit and feeders outside of the building which means it doesn't apply
230.79 only applies to services which doesn't apply.
My gut is telling me 60A is the minimum but I don't know if it's true or how to prove it.
225.39 only applies to branch circuit and feeders outside of the building which means it doesn't apply
230.79 only applies to services which doesn't apply.
My gut is telling me 60A is the minimum but I don't know if it's true or how to prove it.