Yes. I have 208V loads, but required to install a new 480V 200A meter and 480V 200A disconnect. Then, required to have a modular step down unit as well. Does this mean the configuration will be, utility transformer > new 480V 200A meter > 480V 200A disconnect > modular step down unit transformer > 208V loads?Are you asking about a utility meter?
Look up a Square D Mini Power Zone, primary disconnect, xfmr, secondary panel in one enclosure.Does anyone ever had an experience working with a modular step down unit? Where the transformer and panels are in a single enclosure. How do we usually connect the meter on it?