kwikcoupe
Member
- Location
- Washington
I am a facilities technician and this year are going to be performing the sites breaker testing. The large frame rack able breakers will be removed from the gear to be tested on a bench. The small frame 800 amp molded case breakers we have a question. We gave multiple vendors the chance to bid on the project based on a predetermined NETA testing SOW.
Some of the vendors said they were going to remove the building conductors from the breakers to perform testing in place then re-land the conductors and torque. Other vendors said they could use a stab in style cable that inserts into the Allen head of the lug and test across the breaker with the building conductors still landed and the breakers on either end of the conductors open or unracked based on design to isolate the breakers. I did not see in the NETA guidelines either method to be preferred or suggested as a best practice. I have never personally performed these tests but we do need to select a contractor. I can not say if the gear may have voltage transformers or other equipment tied to the system.
Can anyone suggest or explain the benefits either of these methods carries. From what I can tell, to keep the conductors landed the procedure involves less time which then costs less in manpower. It may be less intrusive since you are not touching the conductors. On the other side, complete isolation of the breaker cold be performed with removing the conductors but at nearly twice the cost based on time involved.
We are talking about a few hundred of these breakers to be tested in a few days time. If anyone could provide insight that would be very helpful.
Thank you
Michael
Some of the vendors said they were going to remove the building conductors from the breakers to perform testing in place then re-land the conductors and torque. Other vendors said they could use a stab in style cable that inserts into the Allen head of the lug and test across the breaker with the building conductors still landed and the breakers on either end of the conductors open or unracked based on design to isolate the breakers. I did not see in the NETA guidelines either method to be preferred or suggested as a best practice. I have never personally performed these tests but we do need to select a contractor. I can not say if the gear may have voltage transformers or other equipment tied to the system.
Can anyone suggest or explain the benefits either of these methods carries. From what I can tell, to keep the conductors landed the procedure involves less time which then costs less in manpower. It may be less intrusive since you are not touching the conductors. On the other side, complete isolation of the breaker cold be performed with removing the conductors but at nearly twice the cost based on time involved.
We are talking about a few hundred of these breakers to be tested in a few days time. If anyone could provide insight that would be very helpful.
Thank you
Michael