laketime
Senior Member
I have just started a project but I have some work that is completed and I want to submit for a monthly billing. The issue I have is the bid was broken up by linear feet of conduit. One is a fiber optic conduit so that is straight forward. The street light conduit was listed and bid by linear feet with wire in it. We have installed the conduit but probably will not pull the wire until spring. Would you guys bill straight for the $/lf on the light conduit even though the wire is not in it yet?