Motel

Status
Not open for further replies.

z-men

Member
Location
Michigan
I'm going to up-grade a 100 amp service in a motel to 200 amp.I have about 150 feet of 2/0 I had left from another job, I would like to use that for the service drop which is a straight up 2-inch rigid mast 10 feet up from the meter socket.
Can I use table 310.15(B)(6) for dwellings and use the 2/0 copper or do I have to go to table 310.16 and use 3/0???
I'm thinking that a motel is a dwelling.
 
Status
Not open for further replies.
Top