M Mporter4 Member Jan 31, 2008 #1 I have a 3-phase ,480v,10 hp motor in a hazardous location class 1 div 2 and a question was brought up about a secondary ground that is tied from the motor frame to structural steel;Is this an nec requirement or a like to have?
I have a 3-phase ,480v,10 hp motor in a hazardous location class 1 div 2 and a question was brought up about a secondary ground that is tied from the motor frame to structural steel;Is this an nec requirement or a like to have?
B bphgravity Senior Member Location Florida Jan 31, 2008 #2 This is not an NEC requirement, nor will it serve any purpose.
zog Senior Member Location Charlotte, NC Feb 6, 2008 #6 Then I agree with the 1st two answers you got, not required, no purpose.
don_resqcapt19 Moderator Staff member Location Illinois Occupation retired electrician Feb 6, 2008 #7 Zog, Why would it change if the supply was from an ungrounded delta system? Don