Floyd R Turbo
Member
- Location
- West Des Moines, IA, USA
- Occupation
- Electrical Engineer & Entreprenuer
I'm having a little trouble finding an answer in the NEC to this question:
Let's say that I have a commercial space, such as a ground floor of a high rise apartment building. This space currently has a single 480V panel and is all open space (no dividing walls)
The space now needs to be divided into more than one commercial tenant space: A, B and C.
The 480V panel would be in a dedicated electrical room in the "A" space. This space would not necessarily be readily accessible to the "B" and "C" tenants at all times (i.e., if tenant "A" was closed)
Each space will have 480V loads (HVAC - compressors on roof and air handling units in the tenant space, both with fused disconnects) and 120V loads (lighting & receptacles).
Do the "B" and "C" spaces need to have their own 480V sub-panel for the 480 loads that serve those spaces, or can the 480V loads from all 3 spaces be served from the existing 480V panel in the "A" space?
Similarly, each space would have 120 loads, and these would be done via separate transformers (one for each space). If all 480V loads can be served from the "A" space closet, can all three 480/208 transformers be located in that closet as well, with 120/208 sub-panels then in each tenant space?
I guess this boils down to the question of, for a subdivided commercial/retail space that is leased, does it matter where the circuit breakers are that serve that space?
Let's say that I have a commercial space, such as a ground floor of a high rise apartment building. This space currently has a single 480V panel and is all open space (no dividing walls)
The space now needs to be divided into more than one commercial tenant space: A, B and C.
The 480V panel would be in a dedicated electrical room in the "A" space. This space would not necessarily be readily accessible to the "B" and "C" tenants at all times (i.e., if tenant "A" was closed)
Each space will have 480V loads (HVAC - compressors on roof and air handling units in the tenant space, both with fused disconnects) and 120V loads (lighting & receptacles).
Do the "B" and "C" spaces need to have their own 480V sub-panel for the 480 loads that serve those spaces, or can the 480V loads from all 3 spaces be served from the existing 480V panel in the "A" space?
Similarly, each space would have 120 loads, and these would be done via separate transformers (one for each space). If all 480V loads can be served from the "A" space closet, can all three 480/208 transformers be located in that closet as well, with 120/208 sub-panels then in each tenant space?
I guess this boils down to the question of, for a subdivided commercial/retail space that is leased, does it matter where the circuit breakers are that serve that space?