rwood3444

Member
Okay, I'm getting up to speed on residential after doing commercial and industrial since 1985, damn economy!! I used 220.84 for the 74 apartments we will be doing and have enough raw feeder power. There are exisiting MDP's and 600-800A DP's. As I break out the demand load for floors of apartments and split them to small panel load units to use existing feeds, for say 5 apartments off of a breaker from a DP, do I have to size all feeders to demand load figured for just five apartments (ie. 45% for 5 as opposed to 23% for the entire building)? the building is 120/208 3 phase and I'm using the calculations. Is there anything else I should figure in besides the basics (VA at 3, 3000 sm. appl., 1500 for laundry, nameplate for fixed, ect.)? We are using a KW monitoring for each apartment so it can be charged by the owner for each apartment using CT's on individual apartment feeds. Nifty stuff, hooked into a processor so each apartment's KWH is automatically sent to the main processor and set for billing, no meter reader necessary.
 
Yup, knock it back to 45% for only five units, etc. As always, 310.15(B)(4)(b) as needed if single phase at each unit, but it sounds like you've got it.

Welcome to the forum.
 
Status
Not open for further replies.
Top