Trying to load calc. (14) Welders to be added in a commercial building. Want to ensure I'm doing my calculations correctly. The gist of the question is when to multiply by 1.732, (If the nameplate gives values for 3ph amperes , both Imax & Ieff, do I still multiply by 1.732?)
(14) 3Ph welders (using 630.11b for demand factors)
Nameplate shows - 3PH @208V , Imax - 34A , Ieff - 18A
Lets assume 100% duty cycle for this exercise.
What do yall get for a service size?
(14) 3Ph welders (using 630.11b for demand factors)
Nameplate shows - 3PH @208V , Imax - 34A , Ieff - 18A
Lets assume 100% duty cycle for this exercise.
What do yall get for a service size?