I have inherited a semi-designed project. We have several buildings on an industrial campus housing several industrial processes. The motors for these buildings are fed power from an MCC in a centrally located, but separate building. There was a service entrance installed in a few of these buildings, which consists of a 480V, 3 phase panel. This panel feeds 277V LED lighting, a boiler and some room for expansion. In addition, the boiler building has motors in it, which are fed from the MCC building. And last but not least, the 120VAC feed to this boiler building originates in the MCC building from a lighting transformer. It consists of a few 120V circuits ran to the building with no disconnect or breakers located in the boiler building. Below summarizes the power feeds:
1. 480V service entrance panel in boiler building for 277V LED lighting and heat trace, misc three phase loads, and room for expanision.
2. Motors in boiler building fed from an MCC located in a separate building.
3. 120VAC fed to boiler building from branch breakers located in the MCC building. It consists of three circuits on 20A breakers.
My question is this an acceptable practice (in compliance with NEC and an acceptable approach from a design standpoint)?
1. 480V service entrance panel in boiler building for 277V LED lighting and heat trace, misc three phase loads, and room for expanision.
2. Motors in boiler building fed from an MCC located in a separate building.
3. 120VAC fed to boiler building from branch breakers located in the MCC building. It consists of three circuits on 20A breakers.
My question is this an acceptable practice (in compliance with NEC and an acceptable approach from a design standpoint)?