hcubed
Member
- Location
- Boulder, CO
- Occupation
- PE
Multiple Inverters in "Combiner" Panel 705.12(D)(2) Application Commercial/Industrial
Hi,
I have a generic question regarding multiple inverters in a combiner panelboard in commercial/industrial 3-phase systems.
On a customer's existing main switchgear say we'll be installing a new circuit that goes to a new panelboard where we'll be interconnecting several new inverters (say four 20kW 3-phase inverters at 277/480V) - does 705.12(D)(2) apply to the panelboard? There will be no other loads in the new panelboard (and it will be labeled as such - "do not move or add circuits"). And now let's add one more complication - those inverters are actually bidirectional converters because they're battery systems, so they can technically act as a source or load. They would be controlled so that they're either all generating or all charging (you wouldn't ever have a situation where some were charging and some were generating simultaneously).
If 705.12(D)(2) doesn't apply then you don't have to worry about the 120% rule and you don't have to upsize the bus size on the panelboard, or install an MCB, helping to keep costs down.
Thanks.
Hi,
I have a generic question regarding multiple inverters in a combiner panelboard in commercial/industrial 3-phase systems.
On a customer's existing main switchgear say we'll be installing a new circuit that goes to a new panelboard where we'll be interconnecting several new inverters (say four 20kW 3-phase inverters at 277/480V) - does 705.12(D)(2) apply to the panelboard? There will be no other loads in the new panelboard (and it will be labeled as such - "do not move or add circuits"). And now let's add one more complication - those inverters are actually bidirectional converters because they're battery systems, so they can technically act as a source or load. They would be controlled so that they're either all generating or all charging (you wouldn't ever have a situation where some were charging and some were generating simultaneously).
If 705.12(D)(2) doesn't apply then you don't have to worry about the 120% rule and you don't have to upsize the bus size on the panelboard, or install an MCB, helping to keep costs down.
Thanks.