Montanaboy
Member
I have a project that appears that it is going to have 3 different utilities in one underground duct bank. There will be 13.8kV electric, an 8" gas main and a 10" water main all in the same trench. The electric will be encased in concrete. The rest will be in flowable fill.
Where can I find clearance/ distance/ separation requirements for this scenario? What requirements are there?
Where can I find clearance/ distance/ separation requirements for this scenario? What requirements are there?