Jake's Dad
New member
- Location
- Cecilton, MD
The Electrical Contractor on a current project has installed 33-kv cables through a series of ductbanks & manholes to feed several buildings. The contractor has used different conduits to pull through instead of the conduits directly across from each other. Apparently there was a blockage in some of the conduits when the pull started, so they just pulled through whichever conduit was available and went back and cleared the blockage. (????) Still waiting for proof of conduits being clear. They also blocked empty conduits with cables when they were dressing the cables in the manholes.
The installation has all of us, on the owner's side unhappy with the installation. I'm hoping to find in the code something that tells me that they must change it. I've been through NEC 110, 300 & 310 and haven't been able to put my finger on anything concrete yet. Looking for a copy of ANSI/NECA 1-2006 Standard Practices..., hoping there is something in there.
I've never started a cable pull without knowing conduits were clear and not being able to pull through conduits across from each other. What I consider good workmanship/craftsmanship.
Any advice on a place to find the answer?
The installation has all of us, on the owner's side unhappy with the installation. I'm hoping to find in the code something that tells me that they must change it. I've been through NEC 110, 300 & 310 and haven't been able to put my finger on anything concrete yet. Looking for a copy of ANSI/NECA 1-2006 Standard Practices..., hoping there is something in there.
I've never started a cable pull without knowing conduits were clear and not being able to pull through conduits across from each other. What I consider good workmanship/craftsmanship.
Any advice on a place to find the answer?