I know that several cycles ago all 15 and 20A MWBC's were required to be protected with a 2-P breaker. However, in any of the CEU classes I've taken over the last several years I've been told that they are not required when upgrading a service - only on new construction (at least here in NJ). I had a service upgrade inspected yesterday and the inspector told me that it was required but I objected. I told him that while I understand the reasoning for the 2-P breaker it was not required on a service upgrade. He passed the inspection but I'm wondering if anyone else is running into this with EI's, especially in NJ.
Thanks.