This is about a new jersersy contractor i had worked for not too long ago and this is about one of his customers.
The electrical contractor signed a contract with a home owner to do a 2 family home took out the permit and did the service and rough in ,smokes . That all past inspection. The permit was taken out in 2008.
The h o paid in 3 parts 1. service 2. rough 3. finish. That is how the contract is written . The home owner stopped work after the rough was completed and paid for as much but has stopped doing any work so far. The E C spoke to the home owner and h o just said he is not ready to continue.
The question is how long does the E C have to wait and be responsible for the work to be completed ?
The electrical contractor signed a contract with a home owner to do a 2 family home took out the permit and did the service and rough in ,smokes . That all past inspection. The permit was taken out in 2008.
The h o paid in 3 parts 1. service 2. rough 3. finish. That is how the contract is written . The home owner stopped work after the rough was completed and paid for as much but has stopped doing any work so far. The E C spoke to the home owner and h o just said he is not ready to continue.
The question is how long does the E C have to wait and be responsible for the work to be completed ?