Under the following three senerios, what is the permitted method(s) to identify the grounded conductor(s) within a building (actually, all the feeders and branch circuits of system(s))?
A) 3? 4W 480/277V system.
B) 3? 4W 208/120V system supplied from the 480V system of A) above when the 208/120v system is not in any of the enclosures of system A) except for the bonding jumper required by 250.30(A).
C) The 480/277V system and the 208/120V system utilize the same enclosures at various points through-out the building.
gwz2
A) 3? 4W 480/277V system.
B) 3? 4W 208/120V system supplied from the 480V system of A) above when the 208/120v system is not in any of the enclosures of system A) except for the bonding jumper required by 250.30(A).
C) The 480/277V system and the 208/120V system utilize the same enclosures at various points through-out the building.
gwz2