I've recently inherited a One-Line at work and I'm trying to understand if the scenario below would meet 517.40. It feels like the selective coordination will be difficult and I'm not sure if I'm interpreting 700.10 (b) correctly.
(2) 350kW 480V generators connecting into the generator switchboard. Each generator shown with a breaker and paralleled through controls.
Generator Switchboard Section 1
(2) breakers for the 350kw generator connections
(1) breaker for temp generator / load bank connection.
(1) breaker for the Article 517 equipment
(1) breaker for optional standby controlled to load shed if needed.
Generator Switchboard Section 2
(1) breaker for the Article 517 life safety, treating like article 700 per 517.26
(1) breaker space for a future fire pump.
(2) 350kW 480V generators connecting into the generator switchboard. Each generator shown with a breaker and paralleled through controls.
Generator Switchboard Section 1
(2) breakers for the 350kw generator connections
(1) breaker for temp generator / load bank connection.
(1) breaker for the Article 517 equipment
(1) breaker for optional standby controlled to load shed if needed.
Generator Switchboard Section 2
(1) breaker for the Article 517 life safety, treating like article 700 per 517.26
(1) breaker space for a future fire pump.