2manynotez
Member
- Location
 - Seoul, Korea
 
A quick question.  
Condition:
I have a very large building (5.6 acres under roof) that because of the loads (~ 5MVA) we require two separate entrances at different ends of the building. From what I see, NEW 230 allows multiple entrances under our conditions (amperage, occupancies, use, etc...)
Question:
Is is required by code to interconnect the neutrals for these two loads? I can not find where this is discussed in the NEC
Thanks in advance
	
		
			
		
		
	
				
			Condition:
I have a very large building (5.6 acres under roof) that because of the loads (~ 5MVA) we require two separate entrances at different ends of the building. From what I see, NEW 230 allows multiple entrances under our conditions (amperage, occupancies, use, etc...)
Question:
Is is required by code to interconnect the neutrals for these two loads? I can not find where this is discussed in the NEC
Thanks in advance
				
