erickench
Senior Member
- Location
- Brooklyn, NY
The last part of the above NEC section states the following:
Where the service entrance conductors are paralleled in two or more raceways or cables, the equipment bonding jumper, where routed with the raceways or cables, shall be run in parallel. The size of the bonding jumper for each raceway or cable shall be based on the size of the service-entrance conductors in each raceway or cable.
The last sentence says:"based on the size of the service-entrance conductors in each raceway or cable" and not the sum of the size of each raceway or cable. What is the correct interpretation of this rule? Some people think it's based on the sum.
Where the service entrance conductors are paralleled in two or more raceways or cables, the equipment bonding jumper, where routed with the raceways or cables, shall be run in parallel. The size of the bonding jumper for each raceway or cable shall be based on the size of the service-entrance conductors in each raceway or cable.
The last sentence says:"based on the size of the service-entrance conductors in each raceway or cable" and not the sum of the size of each raceway or cable. What is the correct interpretation of this rule? Some people think it's based on the sum.