I am on a project where we are installing appx. 10 30kva-65kva transformers fed from one distribution panel. All transformers GEC will be tied into a single Grounding Bar that goes to building steel. Am I correct in saying the GEC sizing to the ground at should be the sum of all 10 GEC's to the transformers?