517.33(9) allows for 'selected power circuits needed for effective hospital operation' to be put on the critical branch of the essential electrical system. Does anyone agree this notation allows putting major air handling systems and chillers on the critical branch? The hospital prefers these loads on the critical branch. I dissagree with the concept but can see where there may be a loop hole in the code. The hospital essential electrical system is over 150Kva.