NEC 2005 Art.700 & 701 requires selective coordination for circuit breakers of emergency/standby systems.
In our case there are three circuit breakers (wired in parallel) fed from the generator: two existing (150A C.B. and 400A C.B.) feeding emergency loads of different buildings, and we are adding one new (with 250A C.B.) - standby load for the new Data Center. Stanby load shoud be disconnected first in case of any short circuit.
How in this case selective coordination should be provided?
In our case there are three circuit breakers (wired in parallel) fed from the generator: two existing (150A C.B. and 400A C.B.) feeding emergency loads of different buildings, and we are adding one new (with 250A C.B.) - standby load for the new Data Center. Stanby load shoud be disconnected first in case of any short circuit.
How in this case selective coordination should be provided?