article 220.82 says that the optional method applies to a dwelling unit having the total connected load servedby a single 120/240-volt or 208Y/120-volt set of 3-wire service or feeder conductors with an ampacity of 100or greater.
does it mean that i cannot use the optional method for a dwelling unit supplied by a three phase - 4 wires feeder ? or it is applicable also in this case.
does it mean that i cannot use the optional method for a dwelling unit supplied by a three phase - 4 wires feeder ? or it is applicable also in this case.