Absolute Solar
New member
I have run concealed romex wire in the wall from PV modules on the roof to the inverter. The inspector is interpreting this section of the code to require conduit from the modules to the inverter. I think that if it is surface mounted inside the building the conductors must be in conduit but if concealed behind the dry wall, I think romex is permissible. Any support for this? Thanks