As a professional electrical engineering consultant working for an M&E Design firm, I work mostly in the commercial field doing building design, but occasionally my firm does some power plant design and utility study analysis.
I am bound by code to perform demand load calculations per NEC requirements, however, we all know that these are always much higher than the "actual" demand that a building sees. For example, the NEC demand load for a school may be 750 kW, however, the actual peak kW demand may be less than half that (around 300kW).
Does anyone have or know of any published references, charts, tables, design guidelines, etc.. that I can use to design my minimum generating capacity for the buildings with? My client wants some reassurance that we are using some recognized method of determining this and doesn't want us to use NEC demand because we would end up oversizing the generating capacity needed.
I am bound by code to perform demand load calculations per NEC requirements, however, we all know that these are always much higher than the "actual" demand that a building sees. For example, the NEC demand load for a school may be 750 kW, however, the actual peak kW demand may be less than half that (around 300kW).
Does anyone have or know of any published references, charts, tables, design guidelines, etc.. that I can use to design my minimum generating capacity for the buildings with? My client wants some reassurance that we are using some recognized method of determining this and doesn't want us to use NEC demand because we would end up oversizing the generating capacity needed.