beanland
Senior Member
- Location
- Vancouver, WA
The 2014 NEC Handbook defines a PV interactive system as "A solar PV system that operates in parallel with and may deliver power to an electrical production and distribution network." Under this definition, a large PV plant that is built to put power on the utility grid could be an "interactive system", since even a large utility-scale PV system consumes power when the sun is down, it is a both a load and a generator. It is also interactive in that it reacts to events on the grid. (Even a coal or hydro power plant is a load when not generating.)
However, 90.2(B)(5) states that the NEC has no jurisdiction over utility power plants; and a utility is generally defined as an entity that performs utility functions such as generating, transmitting and delivering power to consumers; and it is widely accepted that power plants and substations are covered by the NESC, not the NEC.
So, what can I point to the NEC that unequivocally shows that a PV power plant that is "utility interactive", including the PV modules, DC wiring, inverters, AC wiring, transformers, etc. is not under NEC jurisdiction?
However, 90.2(B)(5) states that the NEC has no jurisdiction over utility power plants; and a utility is generally defined as an entity that performs utility functions such as generating, transmitting and delivering power to consumers; and it is widely accepted that power plants and substations are covered by the NESC, not the NEC.
So, what can I point to the NEC that unequivocally shows that a PV power plant that is "utility interactive", including the PV modules, DC wiring, inverters, AC wiring, transformers, etc. is not under NEC jurisdiction?