I have a question regarding Cu and AL feeder requirement.
Is there any NEC code requirement for using Cu and Al feeder?
Is there any limitation for using Al feeder?
Sometimes if we need to provide long distance feeder, our clients or contractors will choose Al feeder. But if we need to provide feeder for the panels feeding critical load(For example, feed emergency lighting, critical electrical load), do we need to provide Cu feeder only?
I really appreciate any suggestions.
David
I have a question regarding Cu and AL feeder requirement.
Is there any NEC code requirement for using Cu and Al feeder?
Is there any limitation for using Al feeder?
Sometimes if we need to provide long distance feeder, our clients or contractors will choose Al feeder. But if we need to provide feeder for the panels feeding critical load(For example, feed emergency lighting, critical electrical load), do we need to provide Cu feeder only?
I really appreciate any suggestions.
David