I have a client in WA state that I have supplied four "industrial control panels" to that did not explicitly require labeling of the panels by UL. The panels were supplied without labeling. (I believe all the components internal to the panel are listed however)
The client is now citing NEC 90-7 as a driver that the panels must be listed or labeled. My take is that the AHJ must specify the labeling requirements and that it is not implied by the Code itself. The inspector is an employee of the client (large government site/project).
Any pearls of wisdom on NEC "requiring" listing and labeling? Thanks in advance.