NECA Labor Adjustment Chart

Status
Not open for further replies.

Gategator37

Senior Member
Good afternoon.

When using the NECA Adjustment Chart from the NECA Manual of Labor Units for "change orders" on a new project do you score the points based on the project as a whole or is it based on the "change order" only?

I am working on large project that could potentially score a "very difficult" when using the columns, but my change orders are rather small and would be a "Normal". I am not looking for an excuse to use the "very difficult" column i just want to be fair and reasonable.

Thansk for your help.
 
Unless it is a difficult change order or a after the ceilings are installed I generally require the sub-contractors I deal with to use column 1.

If it is a difficult project I am always willing to listen to any reasonable argument why the labor should be based upon column 2 or column 3.
 