I have been asked to bid on a project to add a 200amp 3phase service to a commercial, srtip store. There are currently three meters, house and two tenant meters each is 200 amp. See Photo
The property owners are going to split one of the two stores so a new 200amp service is needed.
I would like to know how to figure if the existing service can handle this addition? I am unable to read the wire size of the feeder that is supplying these services and on top of that, is there enough room in the 4'x8"x8" trough for this addition?
See Photo
See Photo
See Photo
Any input will be greatly appreciated.
Additional photo links
[ February 15, 2006, 06:57 PM: Message edited by: 1793 ]
The property owners are going to split one of the two stores so a new 200amp service is needed.
I would like to know how to figure if the existing service can handle this addition? I am unable to read the wire size of the feeder that is supplying these services and on top of that, is there enough room in the 4'x8"x8" trough for this addition?
See Photo
See Photo
See Photo
Any input will be greatly appreciated.
Additional photo links
[ February 15, 2006, 06:57 PM: Message edited by: 1793 ]