southernboys
Senior Member
Hey guys need some help bidding a job as in price range. As you saw from the cieling fans I typically come in way too low. So heres the scenario its a wellpump that has a max load of 19.2 amps so Im thinking 30 amp breaker. the pump is 90 foot from the power pack. there will be 53 ft of ditch to be dug. digging could involve a bunch of roots and solid ground. I will need to mount a 60a 4 ckt panel next to the powerpack due to the powerpack being full. Im thimking 500-600 in labor how far off am I? Do I need a dissconect located within sight of the wellpump? If so if I mount a 4x4 do I need a ground rod? what size egc or what code could I find this in? thanks in advance