logan711
Member
- Location
- Las Vegas, NV
i have a contractor running rigid non-metallic under slab for high b=volt electric and transitioning to a rigid metallic 90 under the slab and wanting to transition to a PVC FA to come through slab. how deep do the rigid metallic 90's need to be buried before they must be bonded and, also, if they do run rigid through the slab into a panel or gutter what is an acceptable method of bonding rigid pipe?