Lady Engineer
Senior Member
- Location
- New Jersey
Don't let the P.E. fool you, there are things I still need to be schooled on, and I am willing to ask.
It appears that I'm reviewing plans for a friend, and the engineer ran 4#6 and a ground to the Cooling tower. Now the Cooling Tower does have a VFD also, so I do understand why they would run a neutral, per se, however in your honest opinion, do you think it's necessary since the panel feeding the Cooling Tower has a neutral?
Your take and advice is much appreciated!
It appears that I'm reviewing plans for a friend, and the engineer ran 4#6 and a ground to the Cooling tower. Now the Cooling Tower does have a VFD also, so I do understand why they would run a neutral, per se, however in your honest opinion, do you think it's necessary since the panel feeding the Cooling Tower has a neutral?
Your take and advice is much appreciated!