I would like some of you Inspectors and ECs to chime in on this. I am planning on an addition to my house. I will do the wiring myself. As my house is now, the GEC is tied into the service drop then down 1/2" emt into the house. It is run to the metal water piping in the house and not into the panel. First of all, the water pipes enter the house more than 5' from the service panel. I'm not sure what the code required when the house was built in the mid 80's. My question is, will an inspection on my addition cause me to have to change how my GEC enters and connects in the house? Also, would there be any advantage/reason to running the GEC into the panel and landing on the ground bar regardless of whether I do the addition or not? The panel does have the neutral and ground bar connected by a bracket and bonded to the panel. Need some thoughts on this.
Thanks