wbdvt
Senior Member
- Location
- Rutland, VT, USA
- Occupation
- Electrical Engineer, PE
When a new code edition is issued with new requirements, when does existing equipment need to be updated to meet those new requirements? My understanding has always been that the code that was in force at time of construction/installation is the prevailing code. However, if the equipment is to be replaced, then the current code would be the one that needs to be adhered to. Correct?
For example: As system installed per the 1981 code, does not have a single throw to disconnect the service entrance cables but rather 5 disconnect switches in a single enclosure to accomplish this. Not a code violation, correct?
TIA
For example: As system installed per the 1981 code, does not have a single throw to disconnect the service entrance cables but rather 5 disconnect switches in a single enclosure to accomplish this. Not a code violation, correct?
TIA