boater bill
Senior Member
- Location
- Cape Coral, Fl.
I have a case of scope creep here.:grin:
An existing building and through the creep process, I now have to specify a new building service, generator and transfer switch. My load calculations for the existing building are oversizing the equipment. (Partly my habit of being conservative and not pushing the design envelope. ) There is no new equipment, just an interior remodel. I did have the exhaust fans changed to single phase since fractional hp 3 phase fan motors were ridiculous.
I have the power company billing for the last 2 years.
Can I apply article 220.87 if I meet all 3 conditions?
thanks for the help
An existing building and through the creep process, I now have to specify a new building service, generator and transfer switch. My load calculations for the existing building are oversizing the equipment. (Partly my habit of being conservative and not pushing the design envelope. ) There is no new equipment, just an interior remodel. I did have the exhaust fans changed to single phase since fractional hp 3 phase fan motors were ridiculous.
I have the power company billing for the last 2 years.
Can I apply article 220.87 if I meet all 3 conditions?
thanks for the help