New York net metering replacement

Status
Not open for further replies.

electrofelon

Senior Member
Location
Cherry Valley NY, Seattle, WA
Occupation
Electrician
Anyone familiar with the New York State net metering stuff? For a few years we were heading toward the VDER (value stack) system to replace net metering. I just got this email and I am now confused. Did they nix the VDER and change to the fixed tariff mentioned in the second/third bullet?

At today’s Public Service Commission session, the PSC approved an Order Establishing a Net Metering Successor Tariff. The changes included in the Order will apply to all solar PV projects currently receiving Phase One net metering (NEM): residential projects and behind-the-meter non-residential projects <750 kW. Highlights of the Order include:

  • Phase One NEM will be available for projects interconnected before January 1, 2022. This reflects a one-year delay in the planned implementation due to the impact of the COVID-19 pandemic. Projects that qualify for Phase One NEM will continue to receive it for twenty years from the date of interconnection.
  • Projects interconnected on or after January 1, 2022 will receive NEM but will be charged a monthly Customer Benefit Contribution (CBC) based on the DC nameplate rating of the PV system.
  • The CBC is expected to be initially calculated at between $0.69-$1.30/kW DC monthly, depending on service class and location, and will appear as a charge on the customer’s electric bill.
 