NM cable

Status
Not open for further replies.

wireday

Senior Member
Location
New England
Occupation
Master electrician
Is there any code reference against using NM in a steel butler type building? I do not mean using plastic sleeves in metal studs, just open wiring.
 

retirede

Senior Member
Location
Illinois
It’s done around here all the time. By both farmers and licensed electricians. As long as the runs follow the boards and are secured properly, it makes for a neat installation.

Whether it’s code-compliant or not may depend on the use of the building.
 

kwired

Electron manager
Location
NE Nebraska
Attachment can be a pain but as long as type of use of the building doesn't otherwise prohibit NM cable it is fine.

Keep in mind that in other than dwellings, NM cable generally must be behind a 15 minute finish as well.
 