no bonding grid installed

Status
Not open for further replies.

mh183

Member
there was no grid inspection. walkway was pored,and now its a mess.
what do you guys think if we now installed a grid and pored again or installed pavers rather then rip it up.
 

Dennis Alwon

Moderator
Staff member
Location
Chapel Hill, NC
Occupation
Retired Electrical Contractor
mh183 said:
there was no grid inspection. walkway was pored,and now its a mess.
what do you guys think if we now installed a grid and pored again or installed pavers rather then rip it up.

I would think that a grid on top of a slab would work just, but what do I know...:grin:
 

tonyou812

Senior Member
Location
North New Jersey
I think they should make them rip it up. I see this alot now. People have hot tubs installed and they dont put them in. some people need to learn the hard way.
 

infinity

Moderator
Staff member
Location
New Jersey
Occupation
Journeyman Electrician
Pavers also require the bonding grid. IMO a top coat of concrete over the bonding grid is a good solution.
 