I understand "3 hours or more" for defining continuous loads, but is there a defined limit concerning "shorter duration" noncontinuous loads?
For example, I would expect that transformer inrush (lasting on the order of 0.1 seconds) might not be considered noncontinuous, but would motor inrush be considered noncontinuous?
For example, I would expect that transformer inrush (lasting on the order of 0.1 seconds) might not be considered noncontinuous, but would motor inrush be considered noncontinuous?