DeveloperWithQuestions
Member
- Location
- Florida
- Occupation
- Developer
Hello, the electrical contractor on my project started running their conduit from a CEP to the panels. They are bringing each set of feeders in their own conduits, but hitting large junction boxes where they plan to have both emergency and normal feeders run through. The specs say that emergency system conductors shall be in separate raceway. Does their installation sound like it meets spec or code? The electrician and contractor say the conduits are the separate raceways, but I don't see how it makes sense if they are running through common boxes.